How to estimate drywall from square metres when the board is sold in feet: area per sheet, sheets per m², screws, tape and joint compound per m², with a worked example.

Updated September 16, 2026 · Written for estimators in Ontario and across Canada

Canadian drawings for commercial work are usually in millimetres, and a partition 30 m long and 2.7 m high is easy to measure. Board, though, is still sold in imperial sheets — so the takeoff runs in square metres and the order in sheets. The conversions are simple once, and then they are the same every job.

Sheet sizes in square metres

SheetMillimetresm² a sheetSheets per 100 m²
4 × 8 ft1219 × 24382.9733.6
4 × 9 ft1219 × 27433.3429.9
4 × 10 ft1219 × 30483.7226.9
4 × 12 ft1219 × 36584.4622.4

Thicknesses are the imperial ones in millimetres: 12.7 mm (½ in) and 15.9 mm (⅝ in), usually written 13 mm and 16 mm on drawings. Type X fire-rated board is almost always 15.9 mm.

Board area

For a partition: length × height × faces × layers, less the openings on each face. For a ceiling: length × width × layers. Then add a waste allowance — commonly 5 to 15 per cent depending on how cut-up the walls are — and divide by the sheet area, rounding up.

Finishing rates per square metre

Converted from the common imperial starting rates. They are starting points, not rules — the level of finish and your finishers change them.

ItemImperial ratePer m² of board
Screws (walls, studs at 400 mm)about 32 per 4 × 8 sheetabout 10.8
Paper joint tapeabout 370 LF per 1,000 SFabout 1.21 m
Ready-mixed all-purpose compoundabout 10 US gal per 1,000 SFabout 0.41 L

A worked example

A corridor partition 30 m long and 2.7 m high, one layer each side, with two doors 900 × 2100 mm:

  1. Wall: 30 × 2.7 × 2 faces = 162 m²
  2. Doors: 0.9 × 2.1 = 1.89 m², × 2 doors × 2 faces = 7.56 m²
  3. Board: 162 − 7.56 = 154.44 m²
  4. With 10 per cent waste: 154.44 × 1.10 = 169.88 m² ÷ 2.97 m² = 57.2 → 58 sheets of 4 × 8
  5. Screws: 58 × 32 = 1,856
  6. Tape: 154.44 × 1.21 ≈ 187 m
  7. Compound: 154.44 × 0.41 ≈ 63 L — about four 17 L pails

At 2.7 m, 4 × 8 sheets hung horizontally leave a strip at the top; many crews hang 4 × 9 or 4 × 10 to avoid it. The sheet choice changes the count, so check how the job will be hung.

Doing it on the drawings

PreConstruct AI shows quantities in imperial, metric or both — the company's choice. You click along the walls on a metric or imperial drawing, pick the wall type, and board comes out in sheets with the square metres and the arithmetic beside it, at your own waste and rates.

Free PDF

The takeoff checklist for subcontractors

What to check on the drawing set, drywall and interiors, concrete, wood framing and the bid itself — as a printable PDF. See what's in it.

Your email is used to send you the checklist and nothing else unless you tick the box above. Unsubscribe any time.

Sources

Code tables and published figures change. Check the current Ontario Building Code, your drawings and your engineer before you rely on any number here.