A partition schedule says 92 mm steel studs @ 406 o.c., 0.45 mm, a supplier's price sheet says 3-5/8" 25 ga, and the submittal says 362S125-18. They can all be the same stud. This guide lines up gauges, mils, millimetres and sizes so you can read any of them, then turns a wall into a stud and track order.

Gauge, mils and millimetres

Gauge is the old trade name. Mils are the minimum base-steel thickness in thousandths of an inch, and that's what the standards and submittals use. Canadian drawings often give the thickness in millimetres.

Gauge (as sold)Mils (minimum)Minimum thicknessTypical use on a schedule
25180.45 mm (0.0177 in)Non-structural interior partitions
20 drywall300.75 mm (0.0296 in)Non-structural, stiffer: taller walls, tile, door jambs
20 structural330.84 mm (0.0329 in)Structural (ASTM C955) and some non-structural uses
18431.09 mm (0.0428 in)Structural framing, heavy partitions
16541.37 mm (0.0538 in)Structural framing, curtain-wall backup
14681.72 mm (0.0677 in)Heavy structural framing

The typical-use column is what you'll usually see, not a rule. Which stud a wall needs comes from the partition schedule and the stud maker's limiting-height tables, and the engineer's drawings for anything structural.

The two 20 gauges

“20 gauge” means two different products. The drywall 20 gauge is 30 mil, made to the non-structural standard (ASTM C645). The structural 20 gauge is 33 mil, made to the structural standard (ASTM C955). They look almost the same on the truck. When a schedule or quote just says “20 ga”, find out which one it means, because the price and what the wall can do both change.

EQ studs

EQ (“equivalent”) studs use thinner, higher-strength steel, stiffened with dimples, knurling or ribs, and are sold as performing like the gauge they're named after: a “20EQ” is meant to do the job of a 20 gauge drywall stud. They're non-structural only, and their actual thickness varies by maker. Before pricing an EQ stud against a schedule that names a gauge or a thickness, check the maker's data sheet, and check the fire-rated design if the wall is rated, because some listings name the stud they were tested with.

Reading a stud designation

Makers in Canada and the US use the same four-part code: web depth, type, flange width, thickness. The first two numbers are hundredths of an inch, and the last is mils.

  • 362S125-18: a 3⅝ in stud (S) with 1¼ in flanges, 18 mil. That's the everyday 25 gauge partition stud.
  • 362T125-18: the matching track (T).
  • 600S162-33: a 6 in stud with 1⅝ in flanges, 33 mil.

Stud sizes in inches and millimetres

Web depthMillimetresWhere you see it
1⅝ in41 mmFurring walls, chases, shaft liners
2½ in64 mmThin partitions
3⅝ in92 mmThe common interior partition
4 in102 mmThe common interior partition
6 in152 mmTall walls, plumbing walls, exterior backup

Studs are cut to order or stocked in lengths from 8 to 24 ft. Track comes in 10 ft (3.05 m) pieces. Drawings often round the depths to 41, 64, 92, 102 and 152 mm.

How many studs and how much track

SpacingStuds per metre of wallStuds per foot
300 mm (12 in)3.281.00
400 or 406 mm (16 in)2.460.75
600 or 610 mm (24 in)1.640.50

Add one stud to close each run, then the extras at openings, corners and tees (how many is in the details), then waste. Track is two lengths of wall, top and bottom. Where a wall runs to the deck, the head is usually a deflection track (a deep-leg or slotted track, or a double track), which is a different product and price from the bottom track. The detail shows which.

A worked order

A corridor partition 30 m long, studs at 406 mm, 4 doors taking 3 extra studs each, and 3 tees taking 2 each. Stud waste 5%, track waste 10%.

  1. Layout: 30,000 ÷ 406 = 73.974, + 1 = 75 studs
  2. Extras: 4 × 3 + 3 × 2 = 18
  3. With waste: (75 + 18) × 1.05 = 97.798 studs, at the wall's height
  4. Track: 30 m × 2 = 60 m, with waste 66.0 m ÷ 3.048 m = 22 pieces of 10 ft, before separating the deflection track at the head

Keep studs of different heights and gauges on separate lines. A job with 3 m and 4.2 m walls, or 25 and 20 gauge, is really two or four orders.

Doing it on the drawings

In PreConstruct AI a wall type names its stud and track, the spacing and the extras at openings and corners, the way your partition schedule does. Draw the walls and the studs come out counted at the wall's height, with the track, board, batts and finishing beside them and the arithmetic on each line. The gauge, depth and spacing are the ones on your schedule. It counts and measures, and never picks a stud.

Free PDF

The takeoff checklist for subcontractors

What to check on the drawing set, drywall and interiors, concrete, wood framing and the bid itself — as a printable PDF. See what's in it.

Your email is used to send you the checklist and nothing else unless you tick the box above. Unsubscribe any time.

Sources

Code tables and published figures change. Check the current Ontario Building Code, your drawings and your engineer before you rely on any number here.

The arithmetic in this guide, on your own drawings

Set the scale, measure, pick a type — and every quantity shows the working that produced it, in imperial, metric or both. You check each one; nothing reaches a bid you have not seen.